Under the authority granted to me by board policy, I have approved three change orders over the last three weeks. I am seeking board ratification of these three change orders.
Change Order 21 $37,436
Change Order 22 $14,688
Change Order 23 $21,835
• This is for the addition of asphalt in the visitor bleacher area of the field. This was discussed at the last meeting of the board.
Administrative Recommendation /MOTION/ "I move we ratify the approval of Change Orders 21,22 and 23"